This page was exported from Free valid test braindumps [ http://free.validbraindumps.com ] Export date:Sat Apr 5 11:53:11 2025 / +0000 GMT ___________________________________________________ Title: [Feb-2025] Latest AACE International AACE-PSP exam dumps and online Test Engine [Q26-Q49] --------------------------------------------------- [Feb-2025] Latest AACE International AACE-PSP exam dumps and online Test Engine AACE International AACE-PSP: Selling AACE Certification Products and Solutions QUESTION 26Which of the following is NOT required when initially planning a project?  Resource Identification and leveling.  The duration of each task.  A schedule that identifies tasks required on a project.  Logical relationships between the tasks. QUESTION 27If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?  Reduce the duration of ‘A’ from 20 days to 10 days and replace the relationship from B’ to ‘C with FSO.  Replace the relationship from ‘B’ to ‘C’ with SSO  Reduce the duration of B” from 10 days to 5 days by compressing work effort QUESTION 28In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?  Budgeted cost of work scheduled  Budgeted cost of work performed  Schedule performance index  Actual cost of work scheduled QUESTION 29Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?  450 lifts  300 lifts  45 lifts  150 lifts QUESTION 30Activity C is a  Contentious activity.  Continuous activity.  1-day activity.  Milestone. QUESTION 31Total float is defined as the amount of time an activity can be delayed without impacting  The overall project completion  The buoyancy of a successor activity  The next activity  The end of that activity QUESTION 32Theoretically construct a summary activity for activities 2001 through 2004. Using the “normal” schedule, what is the cost of the hammock?  $271,000  $299,000  $139,000  $289,000 QUESTION 33During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?  Delay product release by 5 days.  Expedite packaging by 5 days.  Expedite printing by 5 days.  Delay manufacturing by 5 days. QUESTION 34What does the heavy, vertical line at “X” represent?  Delay fault line.  The status or data date.  Change-over limits.  International Date Line. QUESTION 35Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?  1001 and 6001  1000. 1001. and 6001  9001 and 6002 and 6002  1000 and 6001 QUESTION 36Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?  36 lifts  24 lifts  30 lifts  48 lifts QUESTION 37Determine the correct formula and date for the late finish for Activity 2002.  LS.2003 – 1 day -> 11.06.01.  LS.2003 – 1 day -> 10-06-01.  LS.2003 + 1 day -> 10-07-01.  LS.2003 – 1 day -> 10-05-01. QUESTION 38Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?  The activities are independent, with Activity 4001 starting 15 days earlier than the start of Activity 5001  These activities are partially concurrent, with Activity 4001 starting 15 days after the start of Activity 3001  These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity 3001. QUESTION 39Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?  After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.  After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.  After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project. QUESTION 40What is the workweek period for this project?  Monday through Friday  Sunday through Friday  Monday through Saturday  Sunday through Saturday QUESTION 41Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?  30 lifts  133 lifts  42 lifts  60 lifts QUESTION 42What day would Activity C complete if the duration of Activity A was reduced by five days?  35  30  45  40 QUESTION 43Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?  6001, 8001, 9001. 9002, 9004. 9005  7001, 8001, 9001. 9003. 9004. 10002  5001,7001.8001,9001,9004,9005  2003,8001.9001.9002,9005,10001 QUESTION 44What is the actual duration as of the status date or data date of Activity B?  7.  3.  0.  4. QUESTION 45Which is NOT an industry-recognized methodology for quantifying critical delay?  Gantt Chart.  Periodic Windows.  Collapsed As-Built.  Time Impact. QUESTION 46The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?  263 CY  368 CM  201 CY  306 CY QUESTION 47For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.  LS.11001 + 25 days.  02-19-04.  EF.11001.  EF.11001 + 1 day. QUESTION 48A driving relationship is _____________________.  A critical relationship.  A finish-to-start relationship.  The link between two related activities.  The link between a predecessor and the activity whose dates it controls. QUESTION 49Which of the following phases does NOT describe the commonly accepted construction life cycle?  Claims and disputes phase.  Installation phase.  Planning and design phase.  Turnover and start-up phase.  Loading … AACE-PSP certification is designed for professionals who are involved in project management and scheduling activities such as planners, schedulers, cost estimators, project managers, project controls analysts, and project engineers. The program includes a rigorous examination process that tests applicants' knowledge and understanding of project scheduling and control techniques, software tools for planning and scheduling, and project execution and control. Passing the AACE-PSP certification exam is a professional achievement that demonstrates a commitment to excellence in project management and the skills necessary to succeed in today's competitive job market. Passing the AACE-PSP exam requires a thorough understanding of project management principles, as well as the ability to apply them in real-world scenarios. AACE-PSP exam is challenging, and candidates must be well-prepared to succeed. Fortunately, AACE International offers a variety of resources to help candidates prepare, including study materials, online courses, and practice exams. By earning the AACE-PSP certification, professionals can enhance their career opportunities and demonstrate their commitment to excellence in project planning and scheduling.   New 2025 AACE-PSP Test Tutorial (Updated 165 Questions): https://www.validbraindumps.com/AACE-PSP-exam-prep.html --------------------------------------------------- Images: https://free.validbraindumps.com/wp-content/plugins/watu/loading.gif https://free.validbraindumps.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2025-02-22 13:28:34 Post date GMT: 2025-02-22 13:28:34 Post modified date: 2025-02-22 13:28:34 Post modified date GMT: 2025-02-22 13:28:34