QUESTION 104
A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.
How should the project manager work with these risk handling strategies?

 
 
 
 

QUESTION 105
A project manager wants to represent the distribution of uncertainty around a risk model element.
However, good data on the variability, of the risk model element has not been collected, and only contains minimum and maximum values.
What curve should the project manager use to represent the distribution?

 
 
 
 

QUESTION 106
A project in the execution phase at the customer’s site has an issue concerning new parts that do not fit properly into a machine. The site project manager cannot find this high probability risk in the risk register.
What action should the site project manager take?

 
 
 
 

QUESTION 107
During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?

 
 
 
 

QUESTION 108
During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

 
 
 
 

QUESTION 109
A risk manager is preparing risk reports to be included in the monthly status report for project executives.
How should the risk manager present the information?

 
 
 
 

QUESTION 110

The project sponsor has asked the project manager how much more a P90 will cost. The sponsor has budgeted for a P40. The project values are in thousands.
How much additional funding would the sponsor need to budget for a P90?

 
 
 
 

QUESTION 111
You are the project manager of the AFD project for your company. You are working with the project team to reassess existing risk events and to identify risk events that have not happened and whose relevancy to the project has passed. What should you do with these events that have not happened and would not happen now in the project?

 
 
 
 

QUESTION 112
A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.
What should the project manager do to avoid this risk?

 
 
 
 

QUESTION 113
A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.
What should the risk management professional do next?

 
 
 
 

QUESTION 114
An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.
What should the risk management expert recommend the agency do first to identify risks and develop the handbook?

 
 
 
 

QUESTION 115
A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago.
What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?

 
 
 
 

QUESTION 116
A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?

 
 
 
 

QUESTION 117
The project manager wants to use an objective method to evaluate the key project risks and develop response plans.
What action should the risk manager propose?

 
 
 
 

QUESTION 118
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.

 
 
 
 

QUESTION 119
An organization is executing two projects – Project A and Project B – simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B.
Which action should the risk manager for Project A take?

 
 
 
 

QUESTION 120
What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?

 
 
 
 

QUESTION 121
The company board is concerned about potential legal action from a high-risk project. What technique can be used to justify risk response decisions taken on this project?

 
 
 
 

QUESTION 122
Your organization, as part of its enterprise environmental factors, has established risk governance to be implemented in each project. Part of this governance is the reassessment of risks within each project. How much detail and repetition in approach for risks to be reassessed for probability and impact?

 
 
 
 

QUESTION 123
During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

 
 
 
 

QUESTION 124
A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercriminals compromising their passwords.
What should the risk manager do?

 
 
 
 

QUESTION 125
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

 
 
 
 

QUESTION 126
Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?

 
 
 
 

PMI-RMP Real Exam Questions and Answers FREE: https://www.validbraindumps.com/PMI-RMP-exam-prep.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below