QUESTION 26
Which of the following is NOT required when initially planning a project?

 
 
 
 

QUESTION 27
If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

 
 
 

QUESTION 28
In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

 
 
 
 

QUESTION 29
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

 
 
 
 

QUESTION 30
Activity C is a

 
 
 
 

QUESTION 31
Total float is defined as the amount of time an activity can be delayed without impacting

 
 
 
 

QUESTION 32
Theoretically construct a summary activity for activities 2001 through 2004. Using the “normal” schedule, what is the cost of the hammock?

 
 
 
 

QUESTION 33
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

 
 
 
 

QUESTION 34
What does the heavy, vertical line at “X” represent?

 
 
 
 

QUESTION 35
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

 
 
 
 

QUESTION 36
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

 
 
 
 

QUESTION 37
Determine the correct formula and date for the late finish for Activity 2002.

 
 
 
 

QUESTION 38
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?

 
 
 

QUESTION 39
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

 
 
 

QUESTION 40
What is the workweek period for this project?

 
 
 
 

QUESTION 41
Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?

 
 
 
 

QUESTION 42
What day would Activity C complete if the duration of Activity A was reduced by five days?

 
 
 
 

QUESTION 43
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?

 
 
 
 

QUESTION 44
What is the actual duration as of the status date or data date of Activity B?

 
 
 
 

QUESTION 45
Which is NOT an industry-recognized methodology for quantifying critical delay?

 
 
 
 

QUESTION 46
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

 
 
 
 

QUESTION 47
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

 
 
 
 

QUESTION 48
A driving relationship is _____________________.

 
 
 
 

QUESTION 49
Which of the following phases does NOT describe the commonly accepted construction life cycle?

 
 
 
 

AACE-PSP certification is designed for professionals who are involved in project management and scheduling activities such as planners, schedulers, cost estimators, project managers, project controls analysts, and project engineers. The program includes a rigorous examination process that tests applicants’ knowledge and understanding of project scheduling and control techniques, software tools for planning and scheduling, and project execution and control. Passing the AACE-PSP certification exam is a professional achievement that demonstrates a commitment to excellence in project management and the skills necessary to succeed in today’s competitive job market.

Passing the AACE-PSP exam requires a thorough understanding of project management principles, as well as the ability to apply them in real-world scenarios. AACE-PSP exam is challenging, and candidates must be well-prepared to succeed. Fortunately, AACE International offers a variety of resources to help candidates prepare, including study materials, online courses, and practice exams. By earning the AACE-PSP certification, professionals can enhance their career opportunities and demonstrate their commitment to excellence in project planning and scheduling.

 

New 2025 AACE-PSP Test Tutorial (Updated 165 Questions): https://www.validbraindumps.com/AACE-PSP-exam-prep.html

         

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below